Digest of news on activities from 28 to 31 August


Digest of news on activities from 28 to 31 August


Installation operations of the well No. 33 at the Kruk field was completed


The length of the flowline is 250 linear metres and the pipe diameter is 89x6 mm. The well is connected to the Kruk gathering station.

The works were carried out within the framework of the project "Oil Well Development in the fields of Sanoat Energetika Guruhi JV LLC".

ERIELL Group acts as the General Contractor for development of the Customer's fields of Sanoat Energetika Guruhi JV LLC located in Fergana Valley, Kashkadarya and Bukhara regions.

At South Mubarek, wells No. 52, 10OE and 11OE were connected to electrochemical protection


On 24 August 2023, ERIELL Group specialists completed works on connection of wells No. 52, 10OE and 11OE of "South Mubarek" field, located in Kashkadarya region, to electrochemical protection equipment.

The works were performed by the Group of Companies as the General Contractor of the project "Programme of Measures to Increase Hydrocarbon Production" implemented jointly with Uzbekneftegaz JSC in terms of construction of oil and gas facilities.

After connection, the gas pipeline was handed over to the Regional Customer - Mubarek Oil and Gas Production Department of Uzbekneftegaz JSC.

Well No. 18 was connected at Tegermen field


On 26 August 2023, ERIELL Group specialists completed works on connection of well No. 18 of "Tegermen" field of Mubarek oil and gas production department of Bukhara region.

The works were performed by ERIELL Group, which acts as the General Contractor of the project "Programme of Measures to Increase Hydrocarbon Production", implemented jointly with Uzbekneftegaz JSC, in terms of construction of oil and gas facilities.

Drilling of exploration well No. 2 was completed at Khatarkum field


On 29 August 2023, specialists of the team No. 37 of Gazli expedition of ERIELL Group successfully completed drilling of exploration well No. 2 of "Khatarkum" field, located in Bukhara region.

The works were performed by ERIELL Group acting as the General Contractor of the project "Programme of Measures to Increase Hydrocarbon Production", which is implemented jointly with "Uzbekneftegaz" JSC, in terms of construction of oil and gas facilities.

Development of well No. 17 at "Kuyi Surgil" was completed


On 28th of August of the current year ERIELL Group specialists completed the works on development of well № 17 of "Kuyi Surgil" field of Ustyurt Gas Production Department of the Republic of Karakalpakstan.

The following works were performed in the process of improvement:
  • installation of wellhead fence, killing unit and flare facility;
  • assembly and concrete pouring of tubing storage area and pad for the aggregate;
  • installation of foundations for the technological pipeline.

ERIELL Group acts as the General Contractor on the Kuyi Surgil field. The works on the part of oil and gas facilities construction are carried out within the framework of Uzbekneftegaz JSC's project "Programme of Measures to Increase Hydrocarbon Production".