Drilling of well #29 "Kuyi Surgil" was completed

Specialists of ERIELL Group's Surkhandarya expedition successfully completed drilling of production well #29 "Kuyi Surgil" ahead of schedule by 42% or 58 days. 

This indicator was achieved due to well-coordinated and well-planned work of drilling crew #36 under the leadership of drilling foremen B. Norkabulov and S. Avezmurotov, as well as other specialists and services of the Group of Companies, which ensure uninterrupted work at the wells.

Kuyi Surgil field is being developed within the framework of the project "Program of Measures to Increase Hydrocarbon Production", implemented by ERIELL Group as a general contractor since 2017 together with JSC “Uzbekneftegaz”.



Training sessions at the temporary storage warehouse "Boysun"

Training sessions were held at the temporary storage warehouse (TSW) "Boysun", during which the effectiveness of actions of the volunteer fire brigade in the context of fire prevention and emergency management was tested. Issues related to fire prevention measures involving the Boysun District EMERCOM were also discussed.

Department Head Ulugbek Kholikov, Junior Inspector Obid Turaev, Rescue Officer Izzatullo Usmonov, and Driver Ubaydullo Dustmurodov participated in the event.

In addition to the above participants, the training was also attended by the staff of the Boysun TSW.

Events of this nature are an important tool in ensuring safety in the workplace. Effective training and education in this area is crucial in minimizing the damage and risks associated with fires.


Well #16 was drilled at “West Tegermen”


On October 6 of the current year, drilling of well #16 of "West Tegermen" field located in Alat district of Bukhara region, was completed.

The drilling rig ZJ-30/1700T was used in drilling and construction of the well, the actual bottom hole of which amounted to 2405 meters.

The well construction works were carried out by specialists of Gazlinskaya expedition of the Group of Companies.

ERIELL Group acts as a general contractor of the project "Program of Measures to Increase Hydrocarbon Production" at "Zapadny Tegermen" field and other facilities of the Customer JSC “Uzbekneftegaz”.



Regular training on prevention of incidents at wells


The Central Engineering and Technology Service (CETS) is a key link in ensuring the safety and efficiency of well operation. The work of the service's engineers is aimed at providing support in complex situations, including drilling, horizon and water-bearing formation, wellbore development, casing running and well development.

A senior complex emergency foreman, an analytical engineer and 11 complex emergency foremen are involved in prevention, development of non-standard emergency tools, and training in the prevention and management of complex emergencies on six expeditions.

Central Dispatch Service develops various incident plans and trains the specialists of each expedition. Training with the drilling crews is also conducted by the CDS lead technologist and complex and emergency foremen.

In addition to the above-mentioned responsibilities, CDS has developed and implemented 20 measures to prevent accidents and ensure safe well wiring at the Bukhara, Karshi, Fergana, Ustyurt, Gazlinsk and Surkhan expeditions.

Central Engineering and Technological Service strives for continuous improvement and upgrading of specialists' training level to minimize risks and ensure successful performance of tasks on ERIELL Group projects.

Bukhara expedition held a meeting on the results of 9 months


On October 11, On Equipment Yards "Beshkent" held a meeting of Bukhara expedition dedicated to the Master's Day, discussion of the results for 9 months, as well as plans till the end of the current year. Within the framework of the meeting the questions on safety measures at production for the third quarter were raised. Foremen, drillers and site supervisors expressed their suggestions on further improvement of work efficiency.

Over the past 9 months, the following drilling crews stood out in terms of production performance and adherence to safe work practices:

Drilling Brigade #30:
1. Oripov Zhobir Muminkulovich.
2.  Sirozhev Sirozh Umarhonovich.
Drilling Brigade #42:
1.  Zhumaev Telman Toshpulatovich.
2. Olimov Bakhrom Askarovich.
Drilling Brigade #104:
1. Khaidarov Elur Khudoykulovich.
2. Akbar Zhumayevich Tukhtaev.

These brigades demonstrated good results, and their efforts were recognized and encouraged at the meeting.