A Summary of Activities from 18th to 30th June


A Summary of Activities from 18th to 30th June

Gas inflow received at Kuyi Surgil No. 27


In the Republic of Karakalpakstan, at the Kuyi Surgil field, ERIELL Group specialists successfully completed the construction and connection of well No. 27. This well achieved an industrial gas flow rate of 168,865 cubic meters per day.

The development of Kuyi Surgil is part of the "Program to Increase Hydrocarbon Production," with ERIELL Group acting as the General Contractor for the project on behalf of Uzbekneftegaz JSC.

 

Completion of ECP Section for Shurtan Gas Pipeline:

ERIELL Group specialists finished connecting the gas pipeline from SP 1-2 "Shurtan" to SP-26 "Shurtan," located in the Shurtan Oil and Gas Production Department of the Kashkadarya region, to the electrochemical protection equipment (ECP). The total length of this gas pipeline is 1,212 km. ERIELL Group served as the General Contractor for the "Program of Measures to Increase the Production of Hydrocarbons," a joint initiative with Uzbekneftegaz JSC.

Installation of Air Defence at Well No. 13-OE "West Kuyi Surgil":

At well No. 13-OE "West Kuyi Surgil," ERIELL Group specialists efficiently installed air defence at the mouth, completing the task 30% ahead of the standard time. The Karshi expedition of the Group of Companies, under the leadership of Air Defence Service Mechanic Khakimov Rovshan Rustamovich, carried out the work.